Planning vs Scheduling — Distinct Roles

RoleResponsibilitiesTime horizon
PlannerScope the work; identify and reserve materials; write the job plan (steps, tools, permits, estimated hours); identify craft skills required; identify safety requirements (isolation, confined space, hot work permits)Works 1–4 weeks ahead; never on reactive work
SchedulerBuild the weekly schedule from the ready-to-schedule backlog; coordinate with operations for equipment access; assign craft personnel; confirm materials are on-site; issue the schedule Monday morning1 week ahead
Supervisor/ForemanExecute the daily schedule; manage exceptions; reassign on reactive priorities; provide feedback on job completionsDay to day

The planner should not take reactive work orders — their job is to work ahead of the execution team, not alongside them. A ratio of 1 planner to 15–20 craft technicians is typical.

Work Order Workflow

  1. Request: Any maintenance need is raised as a work order in the CMMS — by operations, maintenance, or PdM systems. No verbal requests — everything in writing
  2. Approval and prioritisation: Supervisor reviews and assigns priority (Emergency/Urgent/Routine/Shutdown) and approves or rejects. Priority coding determines planning timeline
  3. Planning: Planner scopes the job, identifies parts and tools, writes step-by-step job plan, estimates craft hours and duration, identifies safety requirements, identifies equipment access requirements
  4. Ready-to-schedule: When all materials are available and all pre-conditions are met (permits, equipment access confirmed with operations), the work order moves to the ready-to-schedule backlog
  5. Weekly scheduling: Scheduler selects from the ready-to-schedule backlog to fill craft capacity for the coming week; confirms with operations; issues schedule
  6. Execution: Technicians execute the planned work; record actual hours, materials used, findings, and any additional work identified
  7. Feedback and closure: Supervisor reviews completion, signs off; actual vs planned hours compared; lessons learned fed back to planner to improve future job plans

Backlog Management

The maintenance backlog is the total of all open, approved work orders. A healthy backlog contains enough work to keep the team fully scheduled but is not growing uncontrollably:

Backlog typeTarget levelConcern if
Total approved backlog (weeks of work)3–5 weeks of craft capacity<2 weeks: insufficient work visibility; >8 weeks: growing faster than completion rate
Ready-to-schedule backlog (weeks)1–2 weeks ahead<1 week: scheduling from under-planned work; >3 weeks: scheduling bottleneck
Emergency/urgent work as % of total<10%>20%: reactive culture — planning not effective; investigate why PMs are not preventing failures

Improving Wrench Time

Wrench time (productive time) studies typically reveal that maintenance technicians spend only 25–35% of their working day on actual maintenance tasks. The remainder is lost to:

Time loss categoryTypical %Remedy
Waiting for parts or materials15–20%Pre-kitting: all materials assembled and staged in a kit before the job is scheduled. Never start a job without all materials on site
Waiting for permits to work (isolation, confined space)8–12%Permits pre-applied for during planning; isolation schedule coordinated with operations in advance
Waiting for equipment access (operations)8–12%Weekly scheduling meeting with operations confirms access slots in advance; no more showing up to find the machine still running
Travel and transport5–8%Organise work by area; tool stores located near work areas; vehicle use planned
Looking for information (drawings, manuals)3–5%Job plan includes document references; electronic access to drawings via tablet
Breaks and personal time10–15%Reasonable — do not target further reduction

Key Planning and Scheduling KPIs

  • Schedule attainment: % of scheduled work orders completed in the scheduled week. Target: >85%. Formula: (WOs completed from schedule / WOs scheduled) × 100
  • PM compliance: % of preventive maintenance work orders completed on time. Target: >95% for critical assets
  • Planned work as % of total hours: Hours spent on planned work orders / total maintenance hours. Target: >80%
  • Emergency/corrective ratio: Emergency work hours / total hours. Target: <10%
  • Backlog age: Average age of work orders in the backlog. Rising age indicates scheduling inefficiency or resource shortage