Detailed Comparison

ParameterWire Rope HoistChain Hoist
Capacity range250 kg to 100+ t125 kg to ~20 t (typical <5 t for most applications)
Lifting speed3–30 m/min (often dual-speed)2–8 m/min (single speed typical)
Headroom requiredHigher — drum requires space above hookLower — chain bag folds compactly
Duty classificationM3–M8 (continuous production use)M1–M5 (light to moderate duty)
LifespanLonger with correct maintenanceChain stretches over time — periodic replacement
MaintenanceWire rope inspection, lubrication, drum/sheave wearChain elongation measurement, chain lubrication
Capital costHigherLower
Corrosive environmentsStainless options available (at high cost)Stainless steel chain readily available; better chemical resistance
Explosion-proof (ATEX)Available in Zone 1/2Available (air-operated chain hoists for Zone 1)

Duty Classification (FEM/ISO 4301)

Hoist duty class must match the application — selecting too light a class is a common specification error that leads to premature mechanical failure:

FEM classISO M classApplication
1AmM2Very light — rare use, e.g. maintenance hoists used weekly
1BmM3Light — occasional production use, 2–3 lifts per day
2mM4Moderate — regular production, several lifts per hour
3mM5Heavy — continuous production, >10 lifts per hour
4mM6–M8Very heavy — intensive 24/7 production or steel mill duty

Wire Rope Maintenance

Wire ropes must be inspected and lubricated per LEEA guidance and the manufacturer's schedule. Key inspection points:

  • Broken wires: Discard if >10% of total wires in any rope lay are broken, or if any broken wire is at an end fitting
  • Diameter reduction: Discard if diameter is reduced >10% from nominal (crushing or wear)
  • Corrosion: Surface rust is acceptable with lubrication; internal corrosion or pitting requires replacement
  • Kinks or bends: Discard immediately — kinks cause localised stress concentration and brittle failure
  • Lubricate with wire rope lubricant (not grease) at required intervals — typically every 3 months in outdoor or harsh environments

Chain Hoist Maintenance

Load chains stretch over time. Measure chain elongation with the manufacturer's gauge or by counting links over a given length. Standard discard criterion: replace when elongation exceeds 2% of original length. Also inspect hook throat opening (replace if >5% over nominal), latch operation, and chain guide wear.

Under LOLER (UK) and PUWER regulations, all lifting equipment must be inspected by a competent person at intervals specified in the written scheme of examination — minimum every 6 months for equipment used to lift persons, every 12 months for other lifting equipment, or as specified by a competent person based on risk assessment.